October construction update
Date: 27th October 2025
Article by Rojalin
We’re excited to share the latest progress at SAPPHIRE – C & D, where construction is advancing rapidly and on schedule.
At SAPPHIRE – C, the entire slab work has been successfully completed. Brickwork up to the 5th floor and internal plastering on all floors are now fully finished, marking a major milestone in the journey toward completion.
At SAPPHIRE – D, the 4th slab has been successfully cast, and the columns for the 5th floor are complete, with the next slab scheduled for November. Brickwork on the 3rd floor is actively progressing, ensuring steady momentum across the block.
With every phase, we’re moving closer to delivering exceptional homes that combine quality, comfort, and modern design — all crafted to bring your dream lifestyle to life.