Construction progress Update: Sapphire Blocks C & D

Date: 6th October 2025

Article by Rojalin samal

We are pleased with the steady progress and will continue to share regular updates as the project advances.

SAPPHIRE-C Block

  • Slab work for the entire block has been successfully completed.
  •  Brickwork completed up to the 5th floor.
  • Plastering completed on the 3rd floor and currently in progress on the 4th floor.

SAPPHIRE-D Block

  •  4th slab of the tower has been successfully completed.
  • Brickwork on the 3rd floor is currently in progress.

Stay tuned for more updates as we move closer to making your dream home a reality.